Construction schedule with Swiss public holidays

A construction schedule counts in working days. For that count to hold, it has to know which days are not working days: weekends, public holidays and company shutdowns. In Switzerland this is more demanding than elsewhere, because holidays are governed by the cantons.

Cantonal differences are the norm

Only a few holidays apply nationwide – New Year, Ascension, the National Day and Christmas among them. Much of the rest is decided by the canton: Corpus Christi is observed in the traditionally Catholic cantons, elsewhere work continues. The Geneva Fast is a Geneva day. For a construction project this means the same calendar date can be a holiday in Zug and a full working day in Zurich.

Planning with a generic calendar therefore shifts systematically – sometimes early, sometimes late. On a single task the difference goes unnoticed. Across a chain of dependent tasks it accumulates, and shows up where it is most expensive: at the handover date.

Bridge days belong in the count

When a holiday falls on a Tuesday or a Thursday, the adjoining working day is in practice not worked on many sites. A plan that counts it as productive is more optimistic than reality. Including it is not generosity, it is accuracy.

Shutdowns and blocked periods

  • Company shutdowns of individual contractors – often several weeks, in summer or around Christmas.
  • Periods blocked by conditions, such as noise protection windows or a winter break.
  • Dates that are not work but still need room: acceptances, client meetings, inspections.

These periods are specific to the project and appear in no calendar. They belong in the plan nonetheless, because they shift dates just as a statutory holiday does.

In Menira

A project carries its canton. The holidays follow from it – national and cantonal, for all 26 cantons, bridge days included and across the years the project spans. Your own entries can be added: shutdowns, blocked periods or dates, one-off or recurring every year. When a task moves, the plan keeps counting with these days – dates stay consistent without manual recalculation.

Read on

  • Construction schedule
  • Schedule programme
  • Weekly programme
  • How to plan a construction phase
GlossaryGuidesContactPrivacy PolicyLegal NoticeTerms
© 2026 Menira·Made in Switzerlandv4.5.7